Measures

Implementation period

Cost, RUR mln (excl. VAT)

Status of programme implementation as of December 31, 2010/ major measures introduced

JSC OGK-2 branch – the Stavropol GRES (village of Solnechnodolsk, Izobilnensky region, Stavropol territory)

Reconstruction of the chemical treatment plant

4Q 2006 – 4Q 2012

248.9

Given the annual plan of RUR 1,511.93 thousand, disbursed investment amounted to RUR 19,736.2 thousand, works were executed by means of additional financing

JSC OGK-2 branch – the Surgut GRES-1 (village of Kedrovy, city of Surgut, Khanty-Mansiysk Autonomous District-Yugra, Tyumen region, the Russian Federation)

Installation of a software and hardware package “Stantsiya”

2Q2010 – 2Q2011

20.0

Installation of a software and hardware package “Stantsiya”. Plan – RUR 3,407.3 thousand, disbursed investment amounted to RUR 3,901.0 thousand.

JSC OGK-2 branch – the Serov GRES (city of Serov, Sverdlovsk region, the Russian Federation)

Reconstruction of the 110 kW open switchgear with replacement of air switches for sulphur hexafluoride switches.

1Q2009 – 4Q2012

120.0

Reconstruction of the 110/220 kW open switchgear with replacement of air switches for sulphur hexafluoride switches. Plan – RUR 12,880.1 thousand, disbursed amount – RUR 15,160.8 thousand.


To get more detailed information on modernization program of JSC “OGK-2”, please see the Annual Reports of the Company.

  • 119526, г. Москва
  • Пр-т Вернадского, д. 101, корп. 3, 9-15 этаж
  • Тел.: (495) 428-42-22, 428-42-24
  • Факс: (495) 428-42-23
  • Е-mail: office@ogk2.ru

по-русски