ОАО Вторая генерирующая компания оптового рынка электроэнергии
|
Measures |
Implementation
period
|
Cost, RUR mln (excl.
VAT) |
Status of programme
implementation as of December 31, 2010/ major measures introduced
|
|
JSC OGK-2 branch –
the Stavropol GRES (village of Solnechnodolsk, Izobilnensky
region, Stavropol territory) |
|
Reconstruction of the chemical
treatment plant |
4Q
2006 – 4Q
2012 |
248.9 |
Given the annual plan of RUR
1,511.93 thousand, disbursed investment amounted to RUR 19,736.2
thousand, works were executed by means of additional financing
|
|
JSC OGK-2 branch – the
Surgut GRES-1 (village of Kedrovy, city of Surgut,
Khanty-Mansiysk Autonomous District-Yugra, Tyumen region, the
Russian Federation) |
|
Installation
of a
software and hardware package “Stantsiya” |
2Q2010
–
2Q2011 |
20.0 |
Installation
of a software
and hardware package “Stantsiya”. Plan – RUR
3,407.3 thousand, disbursed investment amounted to RUR 3,901.0
thousand.
|
|
JSC OGK-2 branch – the
Serov GRES (city of Serov, Sverdlovsk region, the Russian
Federation) |
|
Reconstruction
of the 110 kW open
switchgear with replacement of air switches for sulphur
hexafluoride switches.
|
1Q2009
–
4Q2012 |
120.0 |
Reconstruction
of the 110/220 kW open
switchgear with replacement of air switches for sulphur
hexafluoride switches. Plan – RUR 12,880.1
thousand, disbursed amount – RUR 15,160.8
thousand. |
To get more detailed information on
modernization program of JSC “OGK-2”, please see the
Annual Reports of the Company.