ОГК-2

ОАО Вторая генерирующая компания оптового рынка электроэнергии

In the next several years after adjustment with the Ministry of Energy of the Russian Federation, the following investment projects included in the plan of the capital construction of the Company shall be realized:

  1. Steam turbine unit (STU) with installed capacity of 660 MW at the Troitskaya GRES, commissioning period: not later than 11/30/14;
  2. Combined cycle gas turbine unit (CCGT) with installed capacity of 420 MW at the Serovskaya GRES, commissioning period: not later than 11/30/14;
  3. Combined cycle gas turbine unit (CCGT) with installed capacity of 420 MW at the Stavropolskaya GRES, commissioning period: not later than 11/30/16.


Station/Territory

Facility

Commissioning period

Estimated cost of the facility, RUR mln (excl. VAT)

Troitsk GRES, Chelyabinsk region, Troitsk

«Territory of the Troitsk GRES. Construction of power units 660 MW STU (st. ¹ 10, 11) with emphasis on the first start-up facility – power unit st. ¹10»

2014

40,203.08


Station/Territory

Facility

Commissioning period

Estimated cost of the facility, RUR mln (excl. VAT)

Serov GRES, Sverdlovsk region, Serov

«Territory of the Serov GRES. Construction of power units st. ¹9, 10 (420 MW CCGT unit) with emphasis on the first start-up facility – power unit st. ¹9»

2014

19,136.21


Station/Territory

Facility

Commissioning period

Estimated cost of the facility, RUR mln (excl. VAT)

The Stavropol GRES, Stavropol territory, Izobilnensky region, village of Solnechnodolsk

«Territory of the Stavropol GRES. Construction of power unit 420 MW CCGT (st. ¹9)»

2016

15,869.78


Current status of the investment project implementation:


Troitskaya GRES

On August 11, 2010 the Government Decree ¹ 1334-r was released. It provided for construction of the power unit ¹10 with commissioning on November 30, 2014.

In addition to the general contractor contract with CJSC KVARZ – New Technologies ¹1-07 ks of December 14, 2007, an agreement ¹4 of July 14, 2010 was concluded. It stipulated extension of the period for implementation of the project on construction of the power unit ¹10 with 660 MW capacity from 2011 to 2014. It also stipulated elimination of the power unit ¹11 with 660 MW capacity from the volumes of the construction contract.

On September 24, 2010 a positive opinion on the approved portion of design documentation was received after the state expert review. Development of detailed design documentation began. The construction permit was received on December 31, 2010.

Preparatory works have been launched at the construction site: construction of a combined supplementary complex, diesel fuel facilities, a locomotive shop, removal of the existing buildings and constructions.

Serovskaya GRES

On August 11, 2010 the Government Decree ¹ 1334-r was released. It provided for construction of the power unit ¹9 with commissioning on November 30, 2014.

An agreement ¹1 of March 30, 2010 with JSC E4 Group was concluded in addition to the general contractor contract ¹2-07 ks of December 29, 2007 “on performing of general contractor functions on construction of the power unit ¹9 at the Serov GRES”. A contract with JSC TEK Mosenergo ¹ 30/PIR-26/2010 of April 14, 2010 on performing of general design engineer functions was concluded.

Design documentation that is due for approval has been developed and presented for the state expert review.

According to the document the construction site has been transferred to the General contractor.

Stavropolskaya GRES

On August 11, 2010 the Government Decree ¹ 1334-r was released. It provided for construction of the power unit ¹9 with commissioning on November 30, 2016.

Based on this decision, on September 13, 2010 the Company concluded a contract with JSC E4 Group on design of the 420 MW CCGT st. ¹9 of the Stavropol GRES with use of the previous design documentation for the power units ¹9 and ¹10.

  • 119526, г. Москва
  • Пр-т Вернадского, д. 101, корп. 3, 9-15 этаж
  • Тел.: (495) 428-42-22, 428-42-24
  • Факс: (495) 428-42-23
  • Е-mail: office@ogk2.ru

по-русски